Glen Ellyn public works employees now will be able to work on a village-owned sanitary lift station located on College of DuPage property under an agreement approved this week.

The lift station was constructed in the early 1970s on COD property at 580 S. Park Blvd., and while an easement was drafted at the time, it was never executed, village officials said.

Order Reprint Print Article
 
Interested in reusing this article?
Custom reprints are a powerful and strategic way to share your article with customers, employees and prospects.
The YGS Group provides digital and printed reprint services for Daily Herald. Complete the form to the right and a reprint consultant will contact you to discuss how you can reuse this article.
Need more information about reprints? Visit our Reprints Section for more details.

Contact information ( * required )

Success - request sent close

COD and Glen Ellyn officials have had discussions about easements over the past seven years, but it wasn't until this week that the village board and college board both unanimously approved a licensing agreement that grants the village a 20-by-60 foot easement.

It allows village crews to access the site for operation of the lift station and install a standby electric generator while other pumping facilities are upgraded.

Officials say the licensing agreement is an outgrowth of the intergovernmental agreement signed last year by the village, college and DuPage County. That pact ended a protracted legal battle between Glen Ellyn and COD that centered on the degree to which the college was subject to village regulations, particularly over permitting and inspections of COD building projects.

The county now has jurisdictional oversight on the college's 273-acre Glen Ellyn campus.

The lift station gets wastewater from sanitary sewers that originate near Park Boulevard and Butterfield Road -- an area that includes Glenbard South High School and the Arden Courts health care facility.

The agreement stipulates that the village must give COD written notice before it goes on the property. The village also must submit to the college on-site improvement plans -- including installation of the electric generator -- which are subject to the college's approval.

The village is responsible for the costs of operating the station.

Share this page
Comments ()
Guidelines: Keep it civil and on topic; no profanity, vulgarity, slurs or personal attacks. People who harass others or joke about tragedies will be blocked. If a comment violates these standards or our terms of service, click the X in the upper right corner of the comment box. To find our more, read our FAQ.