advertisement

New proceedings ordered in power-line land dispute

SPRINGFIELD, Ill. (AP) - The Illinois Supreme Court has reversed a ruling that had stopped construction of a massive power line through eastern Illinois.

The court's 7-0 ruling Thursday affects 35 Edgar County eminent domain actions by Ameren Transmission Co. to obtain land for the remaining section of a 375-mile cross-state power line.

Justice Bob Thomas' opinion found that a circuit court did not have jurisdiction when it ruled that landowners were denied due process in the eminent domain procedure. The court ordered new proceedings.

The 30-mile segment of the 345,000-volt line from the town of Kansas to Indiana is the last of nine segments to be installed. The completion date is late 2019.

Kansas is 192 miles (309 kilometers) south of Chicago.

___

The case is Ameren Transmission Co. v. Hutchings .

Article Comments
Guidelines: Keep it civil and on topic; no profanity, vulgarity, slurs or personal attacks. People who harass others or joke about tragedies will be blocked. If a comment violates these standards or our terms of service, click the "flag" link in the lower-right corner of the comment box. To find our more, read our FAQ.