After referendum win, District 214 maps out year-round construction timeline

After securing referendum approval from voters for the first time in more than half a century, Northwest Suburban High School District 214 officials have begun planning in earnest for a $295 million capital improvement program across all six schools.

That includes setting an aggressive construction schedule over the next three to four years — with work to be done year-round, while classes are in session — to curb the effects of inflation, and enlisting a team of project managers, architects, financial advisers and other consultants to help with it all.

“This was not a crossing of the finish line, so to speak,” said Superintendent Scott Rowe of the Nov. 3 ballot question that passed 61% to 39%. “It’s actually the start of maybe a marathon.”

After the Cook County Clerk’s office officially certifies the result Nov. 24, district officials plan to issue an initial set of school building bonds in February for work that will occur as soon as next summer, Rowe said.

Issuing the bonds over a 25-year term will yield a yearly tax increase of $218 for the owner of a home valued at $500,000, under initial estimates.

Justin Attaway, the district’s associate superintendent for business services, said the entirety of the referendum debt must be issued within five years, but officials hope to expedite the process. Some projects, he acknowledged, can only be done over the summer months when buildings are empty, such as classroom upgrades, new roofs and boilers.

A detailed, phased plan that will outline the work project by project, building by building, and from start to finish will be part of a regularly updated dashboard on the district website. It will show budgeted costs, expenditures, outstanding commitments and anticipated final costs, according to Attaway and Rowe.

“The community trusted us by saying yes,” Rowe said. “Now we will show them our progress and show them that that trust was well placed, and that we ensure we’ll keep it.”

Given the size and complexity of the construction program, the school board late last week inked an agreement with Turner & Townsend Heery to oversee the process as owner’s representative. The firm is tasked with monitoring budgets and schedules, reviewing costs and change orders, and serving as a check against the architects and construction vendors hired by the district, officials said.

For example, Jason Sparks, the firm’s Chicago office director, said he and co-workers sit in on design meetings with architects to suggest ways to build that might be cheaper in terms of materials, labor and lead times. Then once construction begins, Sparks said they review pay applications to ensure cost, schedule and quality.

While the firm doesn’t provide a total cost of compensation upfront, its fees-to-savings ratio is usually 4:1, he said.

“It’s stretching the dollar,” Sparks said. “It’s $100,000 that we didn’t have to spend here that now your team can decide where else to use that money for other investments.”

The board last week also approved a new agreement with Arcon Associates, the architecture firm that identified some $850 million in potential building upgrades as part of a facilities assessment four years ago that was the impetus for the referendum. Last month, the board also signed a contract with another firm, Wold Architects and Engineers, to assist with the design process.

Even before the board voted to place the question on the ballot this summer, those two firms were among 20 that responded to a district request for qualifications for architectural services.