Lombard’s Main Street work entering stretch run

Lombard public works crews on Tuesday will begin the final phase of the Main Street Rehabilitation project that includes replacement of curbs and gutters, replacement of some driveway aprons and concrete pavement replacement on Main between Roosevelt Road and 15th Street, officials said.

Officials say the work is expected to take about a month and traffic will remain open throughout the remainder of the project.

Residents living in the construction area will be unable to access their driveways during curb work and roadway paving. Parking permits will be provided for residents affected by construction.

For details, contact the public works department at (630) 620-5740.