Route 21/137 work wrapping up:

On Monday, northbound and southbound traffic on Milwaukee Avenue (Route 21), north of Route 137, will be shifted from Janas Court north to the end of the project to allow contractors to complete various work. That work will include median landscaping, crossover restoration, curb and gutter placement. All lanes are scheduled to be open with substantial completion of the widening project, including activated new traffic signals, permanent lighting, final landscaping and striping, scheduled for May 21. The contractor has 10 working days after that date to complete any remaining work.

Article Comments
Guidelines: Keep it civil and on topic; no profanity, vulgarity, slurs or personal attacks. People who harass others or joke about tragedies will be blocked. If a comment violates these standards or our terms of service, click the "flag" link in the lower-right corner of the comment box. To find our more, read our FAQ.