Rolling Meadows braces for Golf Road construction

Project expected to cause headaches for nine months

hello
Success - Article sent! close
  • Construction is scheduled to begin March 1 on a project to widen and modernize the intersection of Golf and Wilke roads in Rolling Meadows. The bad news for drivers is that it's expected to take nine months to complete the $5.3 million project.

       Construction is scheduled to begin March 1 on a project to widen and modernize the intersection of Golf and Wilke roads in Rolling Meadows. The bad news for drivers is that it's expected to take nine months to complete the $5.3 million project.
    Bill Zars | Staff Photographer

  • Construction on Golf Road in Rolling Meadows will stretch from Continental Tower Drive to Salt Creek Bridge.

       Construction on Golf Road in Rolling Meadows will stretch from Continental Tower Drive to Salt Creek Bridge.
    Bill Zars | Staff Photographer

  • About 70,000 cars pass through the intersection of Golf and New Wilke roads each day in Rolling Meadows.

       About 70,000 cars pass through the intersection of Golf and New Wilke roads each day in Rolling Meadows.
    Bill Zars | Staff Photographer

 
 

Only a short stretch of roadway will be rebuilt to modernize the intersection of Golf and New Wilke roads in Rolling Meadows, but officials expect a lot of grief during the approximately nine months of construction.

Officials hope construction starts March 1 and be complete, with all lanes open to traffic, by the end of the year.

At least one lane of traffic in each direction, as well as all business driveways, will be open throughout construction.

However, with 70,000 cars passing through the intersection each day, officials urge anyone who possibly can take another route to do so.

The project will cost $5.3 million, less than the $7 million initially expected, said Fred Vogt, the city's director of public works. All but $500,000 will come from federal and state programs.

Construction on Golf will stretch from Continental Tower Drive to Salt Creek Bridge. New Wilke, which dead-ends into the Continental Towers parking lot, was rebuilt a few years ago.

When the project is finished, Golf will be widened to three through lanes in each direction plus turn lanes. This includes two left-turn lanes from eastbound Golf to northbound Wilke that are expected to see considerable traffic.

Traffic signals, storm sewers, sidewalk, bike path, driveway entrances and landscaping are among the improvements planned in the project city engineers have had in the works for several years. The contractor is Martam Construction Inc. of Elgin.

The city will update the work's status on its website, www.ci.rollingmeadows.il.us.

Officials plan to provide information on the Golf Road construction and discuss an ongoing Regional Transportation Authority study of alternative transportation options in the area with people who work in major office buildings starting today.

Share

Interested in reusing this article?

Custom reprints are a powerful and strategic way to share your article with customers, employees and prospects.

The YGS Group provides digital and printed reprint services for Daily Herald. Complete the form to the right and a reprint consultant will contact you to discuss how you can reuse this article.

Need more information about reprints? Visit our Reprints Section for more details.

Contact information ( * required )

Name * Company Telephone * E-mail *

Message (optional)

Success - Reprint request sent Click to close
Comments ()
Guidelines: Keep it civil and on topic; no profanity, vulgarity, slurs or personal attacks. People who harass others or joke about tragedies will be blocked. If a comment violates these standards or our terms of service, click the X in the upper right corner of the comment box. To find our more, read our FAQ.
    help here