Test runs start for Panama Canal expansion

AGUA CLARA, Panama (AP) - The first test runs along the newly expanded Panama Canal began Thursday as tugs nudged the bulk cargo carrier Baroque into the first level of locks on the Atlantic side of the canal.

The expanded locks have increased the technical difficulty of maneuvering larger ships through the canal. But some of the challenges were eased by the weather during the test run, with it being a sunny day without much wind.

And the Baroque, at 836 feet in length, is not as big as the New Panamax behemoths, which measure up to 1,200 feet and which will begin transiting the waterway when it is opened.

The Baroque, rented for the operation, wasn't carrying cargo on the first run through the Agua Clara locks, which took about three hours.

"The test went very well," said engineer Giuseppe Quarta of Salini Impregilo, one of the firms contracted to build the expansion. "Today, we weren't worried about the time."

Workers and canal administrators were on hand to witness the tests, and workers unfurled a banner that read, "We built the canal."

The formal opening of the expanded canal is scheduled for June 26, about a year and a half behind schedule.

The $5.25 billion expansion is expected to double the canal's capacity, tap new markets such as liquid natural gas shipments and cut global maritime costs by an estimated $8 billion a year.

Under the new system, tugboats have to engage in tricky maneuvers in a confined space inside the locks themselves to keep the bulky New Panamaxes from banging into the walls or even crushing the tugs if they lose control.

Under the old system, tugboats' engagement with ships had been limited to guiding them in open waterways and to the entrance of the locks, where powerful locomotives known as "mules" took over, latching on and keeping the vessels in place as the water level is raised or lowered.

Panama Canal workers watch the Malta flagged cargo ship named Baroque, a Post-Panamax vessel, navigate the Agua Clara locks during the first test of the newly expanded Panama Canal, in Agua Clara, Panama, Thursday, June 9, 2016. The canal's expansion project will be officially inaugurated on June 26. (AP Photo/Arnulfo Franco) The Associated Press
Workers watch a Malta flagged cargo ship named Baroque, a post-Panamax vessel, as it becomes the first post-Panamax vessel to navigate through the Agua Clara locks in the newly expanded Panama Canal, in Agua Clara, Panama, Thursday, June 9, 2016. The canal's expansion project will be officially inaugurated on June 26. (AP Photo/Arnulfo Franco) The Associated Press
Workers take selfies with the Malta flagged cargo ship named Baroque, a post-Panamax vessel, as it navigates the Agua Clara locks during the first test of the newly expanded Panama Canal in Agua Clara, Panama, Thursday, June 9, 2016. The canal's expansion project will be officially inaugurated on June 26. (AP Photo/Arnulfo Franco) The Associated Press
Workers take photographs of the Malta flagged cargo ship named Baroque, a post-Panamax vessel, as it navigates the Agua Clara locks during the first test of the newly expanded Panama Canal in Agua Clara, Panama, Thursday, June 9, 2016. The canal's expansion project will be inaugurated on June 26. (AP Photo/Arnulfo Franco) The Associated Press
A tourist watches a Malta flagged cargo ship named Baroque, post-Panamax vessel, on Gatun Lake after the ship was the first to pass through the newly expanded Panama Canal, in Agua Clara, Panama, Thursday, June 9, 2016. The canal's expansion project will be officially inaugurated on June 26. (AP Photo/Arnulfo Franco) The Associated Press
Article Comments
Guidelines: Keep it civil and on topic; no profanity, vulgarity, slurs or personal attacks. People who harass others or joke about tragedies will be blocked. If a comment violates these standards or our terms of service, click the "flag" link in the lower-right corner of the comment box. To find our more, read our FAQ.