Crews facing deadline on Indiana wind farm project

Associated Press/2008   Wind turbines from the Maple Ridge Wind Farm tower over a farm in Lowville, N.Y. The $400 million Maple Ridge wind project, the largest in New York state, brought money and jobs and a sense of prosperity to a place that had given up.

Associated Press/2008 Wind turbines from the Maple Ridge Wind Farm tower over a farm in Lowville, N.Y. The $400 million Maple Ridge wind project, the largest in New York state, brought money and jobs and a sense of prosperity to a place that had given up.

 
 1 of 1 
 
text size: AAA
By Associated Press

WINDFALL, Ind. -- Construction crews are hustling to beat a Dec. 31 deadline to finish 125 turbines in the first phase of a wind farm that is eventually planned to reach into four central Indiana counties.

Project developer E-on Climate & Renewables needs to have the turbines in operation before current federal tax credits for wind energy expire at year's end, the Kokomo Tribune reported Friday.

Advertisement

Crews are working overnight shifts to finish building 69 turbines in eastern Tipton County and 56 in northern Madison County, said Andy Melka, project manager for the Wildcat Wind Farm.

Melka said 75 of the electricity-generating turbines -- each standing about 400 feet tall -- have been completed and crews are working from 7 p.m. to 7 a.m. only because the winds are calmer.

"We're still on schedule to have all the turbines up and operating by Jan. 1," Melka said.

The Chicago-based company plans in future phases to build nearly 200 more turbines in Tipton, Howard and Grant counties in the area about 40 miles north of Indianapolis.

Melka said the wind farm's maintenance and control center building near the Tipton County town of Windfall will be ready by the end of December.

E-on said it is spending about $400 million on the wind farm's first phase.

Whether the project's future phases are built might depend on whether Congress extends a tax credit based on how much electricity is produced by a wind farm. The Obama administration supports extending the credit.

Matt Tullis, a spokesman for E-on, said the company was optimistic about the credit being extended and wasn't certain about a proposal that would phase out the credit over five years.

"We would have to see how the five-year phase out is structured," Tullis said. "A longer extension will be beneficial. It would have an impact."

Comments ()
We are now using Facebook comments to offer a more inclusive, social and constructive discussion. Guidelines: Keep it civil and on topic; no profanity, vulgarity, slurs or personal attacks. People who harass others or joke about tragedies will be blocked. If a comment violates these standards or our terms of service, click the X in the upper right corner of the comment box. To find our more, read our FAQ.

This article filed under

Latest Video

MostViewed

Today
Yesterday
Most Commented
Top Jobs

    View all Top Jobs Place a job ad

    MarketsReport

    DHExtras

       
    • Newspaper next section - Newspaper next section Report card checker - report card checker
    • Dh innovation award 2 - Dh innovation award 2 Zillow /real estate page
    • Discuss refer On Guard series
    • Newspaper archives -- Monday or anyday Mike North

    FacebookActivity

    BusinessDirectory

    Connect with a business or service in your area fast. First select a town, then enter a search term or choose one of the listed popular searches:

    Don't see your town listed? Visit our full directory to begin your search.