Keystone XL foes question proposed route through Nebraska

LINCOLN, Neb. (AP) - Opponents of the Keystone XL pipeline questioned its proposed pathway through Nebraska on Tuesday in hopes that state regulators will reject or reroute it, a decision that would create more delays for the 9-year-old project.

But pipeline builder TransCanada defended its proposal to the Nebraska Public Service Commission, arguing that the company's "preferred route" makes the most sense and causes the least amount of disruption.

The proposed pipeline faced another day of scrutiny in a hearing before the Nebraska Public Service Commission, whose five members must decide whether the Keystone XL serves the public interest. Approving the project would allow TransCanada to gain access to holdout landowners' property using Nebraska's eminent domain laws.

The 1,179-mile crude oil pipeline has faced relentless criticism from environmental groups, Native American tribes and a well-organized minority of Nebraska landowners who don't want the project cutting through their property. Business groups and some unions support the Keystone XL, saying it will provide jobs and property tax revenue for local governments.

Opponents argue that, if it wins approval, the Keystone XL should run along the same path as the original Keystone pipeline, a line through eastern Nebraska that was completed with little opposition in 2010. TransCanada's preferred route would carry crude oil roughly 275 miles through Nebraska, whereas the original Keystone route only stretches 210 miles, said Brian Jorde, an attorney for the landowners.

Company officials have said their preferred route is the most direct way to transport oil from Alberta, Canada, to an existing pipeline in Steele City, Nebraska. Rerouting the pipeline would add millions of dollars to the project's $8 billion price tag.

Because it would travel along a nearly straight path, company officials said their preferred route would affect the least amount of land. TransCanada considered other routes, including one that would have run along Interstate 90 in South Dakota, but rejected them because they were longer, said Meera Kothari, a company engineer.

The most direct path "lends itself to a diagonal route through Alberta, Montana, South Dakota and Nebraska," Kothari said.

The company has also argued that the route through neighboring South Dakota is already set, thus requiring it to cross the border at a point near Mills, Nebraska.

The arguments didn't sit well with Art Tanderup, a farmer who grows corn, soybeans and rye on land the pipeline would traverse near the town of Neligh, in northern Nebraska.

Tanderup said he was worried construction would irreparably disrupt the worms, microorganisms and air pockets he has cultivated in his soil, despite the company's promises to restore the land to its original state.

"Basically, it's going to ruin 13 years of no-till farming," he said.

On Tuesday, a leading advocate for Nebraska landowners who oppose the pipeline argued that South Dakota's route wasn't set in stone.

"We've been here for two days of hearings in which we've heard witness after witness say that we have to approve a route with a fixed starting point because the South Dakota Public Utilities Commission approved it, but all the South Dakota Public Utilities commission did was to grant a construction permit," said Dave Domina, an Omaha attorney.

The Nebraska Public Service Commission must decide by Nov. 23 whether to approve or reject the project, based on evidence presented at hearings that could continue through Friday. The elected commission is comprised of four Republicans and one Democrat.

Outside the hearing, about 40 Native American tribe members and supporters gathered to protest the project. The tribes voiced concerns about the pipeline contaminating the state's groundwater.

"We just don't think there's a need for this," said Larry Wright Jr., chairman of the Ponca Tribe of Nebraska.

___

Follow Grant Schulte on Twitter at https://twitter.com/GrantSchulte

An unidentified youth yawns as he stands amidst members of native American tribes who were holding a prayer during a rally outside the building where the Nebraska Public Service Commission was holding a hearing on the fate of the Keystone XL pipeline, in Lincoln, Neb., Tuesday, Aug. 8, 2017. The Nebraska Public Service Commission is on Day 2 of a five-day public hearing to decide whether to approve the Keystone XL pipeline which would transport oil from tar sands deposits in Alberta, Canada, across Montana and South Dakota to Nebraska. (AP Photo/Nati Harnik) The Associated Press
Omaha attorney Brian Jorde, right, talks to attorney Dave Domina during a hearing before the Nebraska Public Service Commission in Lincoln, Neb., Tuesday, Aug. 8, 2017. Jorde had asked Jon Schmidt, a consultant for pipeline builder TransCanada, why the company hadn't proposed running the new Keystone XL pipeline along the original Keystone pipeline, which was finished in 2010. The Nebraska Public Service Commission is on Day 2 of a five-day public hearing to decide whether to approve the Keystone XL pipeline which would transport oil from tar sands deposits in Alberta, Canada, across Montana and South Dakota to Nebraska. (AP Photo/Nati Harnik) The Associated Press
Jon Schmidt, a consultant for pipeline builder TransCanada, answers a question during a hearing Tuesday, Aug. 8, 2017, before the Nebraska Public Service Commission in Lincoln, Neb. Omaha attorney Brian Jorde had asked Schmidt why the company hadn't proposed running the new Keystone XL pipeline along the original Keystone pipeline, which was finished in 2010. The Nebraska Public Service Commission is on Day 2 of a five-day public hearing to decide whether to approve the Keystone XL pipeline which would transport oil from tar sands deposits in Alberta, Canada, across Montana and South Dakota to Nebraska. (AP Photo/Nati Harnik) The Associated Press
Landowner Art Tanderup, of Neligh, Neb., holds a bag of soil from his property as he testifies before the Nebraska Public Service Commission in Lincoln, Neb., Tuesday, Aug. 8, 2017, on the proposed pipeline that is to run through his land. The Nebraska Public Service Commission is on Day 2 of a five-day public hearing to decide whether to approve the Keystone XL pipeline which would transport oil from tar sands deposits in Alberta, Canada, across Montana and South Dakota to Nebraska. (AP Photo/Nati Harnik) The Associated Press
Article Comments
Guidelines: Keep it civil and on topic; no profanity, vulgarity, slurs or personal attacks. People who harass others or joke about tragedies will be blocked. If a comment violates these standards or our terms of service, click the "flag" link in the lower-right corner of the comment box. To find our more, read our FAQ.