advertisement

Fort Wayne City Council approves tunnel project contract

FORT WAYNE, Ind. (AP) - A $187.7 million construction contract has been approved to build the Three Rivers Overflow Reduction and Protection Tunnel in northeastern Indiana.

The project is part of a long-term plan to reduce the average number of combined sewer overflows in Fort Wayne from 76 to four. Construction is expected to take 4ˆ½ years.

The Fort Wayne City Council on Tuesday awarded the contract to Salini Impreglio/S.A. Healy Joint Venture - the lowest of five bidders, the Journal Gazette (http://bit.ly/2pNIu7c) reported.

This will be the joint venture's fourth combined sewer overflow project.

Tunnel boring machines will run 24 hours a day and five or six days a week, said Mike Kiester, city Utilities Engineering manager.

The massive project is expected to create local jobs.

"We're proposing to go almost 25,000 feet, or five miles, starting at our east Dwenger site next to our water pollution control plant, basically following the Maumee River and then the St. Marys River down to the northern end of Foster Park," Kiester said.

Indianapolis is undertaking a similar project. Work began in 2012 on building 27 miles of 18-foot diameter tunnels as part of a $1.6 billion project aimed at reducing the release of raw sewage into Indianapolis' rivers.

Construction is expected to continue until 2025.

___

Information from: The Journal Gazette, http://www.journalgazette.net

Article Comments
Guidelines: Keep it civil and on topic; no profanity, vulgarity, slurs or personal attacks. People who harass others or joke about tragedies will be blocked. If a comment violates these standards or our terms of service, click the "flag" link in the lower-right corner of the comment box. To find our more, read our FAQ.