St. Charles street resurfacing program gets underway
The City of St. Charles is beginning its 2015 Street Program Resurfacing project June 29, weather permitting.
Letters have been mailed to area residents who may be affected by the construction, with the exception of Peck Road where roadway construction signs will be placed in advance of that work starting.
2015 STREET PROGRAM
Street Name From To Location
8th Court Oak Street South End West
Avalon Court S. 15th Street West End West
Crabapple Lane Persimmon Drive Persimmon Drive East
Dukane Drive Stone Drive Kirk Road East
Greenwood Lane Oxmoor Court N. End of Red Gate Park West
Mockingbird Court Greenwood Lane West End West
North Tyler Road East Main Street Allen Lane East
Oxmoor Court Greenwood Lane East End West
Peck Road Route 38 South of Dean Street West
South 8th Street Oak Street Indiana Street West
South 10th Avenue South Avenue Indiana Avenue East
Stone Drive Production Drive Dukane Drive East
Walnut Avenue South 2nd Avenue South 5th Avenue East
Project Dates (Dates are weather-permitting and subject to change)
• West Side: June 29-Aug. 15
• East Side: July 13-Aug. 15
• North Tyler Road: August to October, pending IEPA permit approval
• Peck Road: July - September
"It's important to have streets in good working order for safe, reliable transportation throughout the community," said Civil Engineering Project Coordinator Gary Long. "The city works hard to keep our streets and infrastructure well-maintained."
Regular updates are available on the 2015 Street Program page on the City's website at www.stcharlesil.gov/projects. For more information, contact Gary Long at glong@stcharlesil.gov or (630) 377-4486.